How do I determine the value of OEE?

By Keith Mobley, CMRP of Life Cycle Engineering
As appeared on www.ReliablePlant.com

Overall equipment effectiveness (OEE) can be an accurate representation of overall plant performance. Derived from Total Productive Maintenance (TPM) and the Toyota Production System (Lean), OEE is a single, calculated value that represents the plant’s effectiveness in three key performance indicators: 1) availability or runtime, 2) production rate, and 3) quality rate. This straightforward value was intended to be the product of these three values, but has become a convoluted, almost infinite variation of calculations.  
 
The correct calculation for OEE is the product of the availability, production and quality rates and should be calculated as follows:

Availability Rate

Availability rate is the actual production runtime for a specific time interval divided by the “planned” runtime for the same interval.  For example, an asset that is planned and scheduled to operation eight (8) hours per day, five (5) days per week has a total availability of forty (40) hours.  If it has an actual runtime of twenty (20) hours, the resultant Availability Rate is fifty (50%) percent.

Production Rate

Production rate is the actual gross units produced for a specific time interval divided by the number of units that should have been produced. Technically, the denominator in this case should be the ideal rate as defined by the asset’s design specifications, but in most cases assets are operating well above the original “nameplate” production rate.  Therefore, the best demonstrated production rate should be used for this calculation.  Best demonstrated is simply the best sustainable rate, based on asset history that
your plant has been able to achieve.  For example, when an asset produces 1,000 units per hour and its best demonstrated rate is 2,000 units per hour, the resultant Production Rate is 50%.

Quality Rate

Quality rate should be straightforward.  It is the total quality units produced divided by the total or gross units produced.  Total quality units is defined as the total (gross) units produced minus all scrap, rejects, reworks and any other units that cannot be sold as prime.  For example, if the asset produces 1,000 total units but 100 units are rejected, the numerator becomes 900 and the denominator is 1,000 or a Quality Rate of 90%.
 
Once these three values are determined, the final OEE calculation is simply the produce of the three values, expressed as percentages, or 50% x 50% x 90% or 22.5%.

© Life Cycle Engineering, Inc.

Reliability Excellence (Rx) Logo

For More Information

843.744.7110 | info@LCE.com

 

Share This

Share on Facebook Share on Twitter Share on LinkedIn Share via email